Colocation · Colo

Renting space, power and cooling in a shared facility, in wholesale (large blocks) or retail (rack-level) form.

Current numbers

~24–36 mo construction once power is secured; grid connection waits exceed 4 yr in primary markets and can overlap construction / ~6–12 mo fit-out / days–weekstime-to-power: greenfield self-build vs wholesale colo (live 50k+ GPU cluster) vs neocloudas of 2026-08-26 · register ↗
~1.05–1.75x by lease profileDSCR rating-criteria band (BBB) for data-center project debt by lease profile — NNN lease ~1.05–1.10x, long-term contracted ~1.20–1.35x, colocation ~1.30–1.75xas of 2026-06 · register ↗
18–24 moMastt’s April 2026 greenfield hyperscale-campus construction estimate; colocation has a separate 12–18-month estimateas of 2026-04 · register ↗