Lead-Time Tracker

The lead times that set every AI data center schedule — pulled live from the guide's numbers register, each with an as-of date and a canonical chapter. The pattern to internalize: the schedule is set by the electrical chain, not the building or the GPUs.

Grid interconnection & power

The critical path of the whole build — the queue is measured in years, not months.

Lead timeFigureAs ofChapter
24–36 mo / 6–12 mo / days–weekstime-to-power: greenfield self-build vs wholesale colo (live 50k+ GPU cluster) vs neocloud2026Ch 1.6
~3–7+ yrUS large-load grid interconnection lead time end-to-end; up to ~10 yr in worst queues — the gate behind self-build2026Ch 1.6
Transformers

The single longest-lead component; ordered before design freeze or the date slips.

Lead timeFigureAs ofChapter
~128–160+ wkHV power-transformer lead time (~128 wk standard, ~144 wk GSU, up to ~60 mo constrained); the co-equal gate2025–2026Ch 3.2
~128 wkHV/substation transformer lead time (≈144 wk GSU; up to ~60 mo constrained) — OFE-by-default, pre-GC2025-Q2Ch 2.2
~144 weeksGSU transformer lead time (standard power transformer ~128 wk); up to ~60 mo in constrained markets2025-Q2Ch 2.3
~128-144 wkHV / GSU power-transformer lead time setting equipment-delivery risk in supply agreements; up to ~60 mo constrained2025-Q2Ch 2.4
Switchgear, generators & turbines

The rest of the electrical chain — each one long enough to be schedule-critical.

Lead timeFigureAs ofChapter
52–70 weeksdiesel genset lead time (1.25–3.25 MW class); largest engines to ~78 wk2026-05Ch 2.3
~45–80 wkHV switchgear lead time, typical; up to 3–5 years for HV GIS/full substations in constrained markets; MV eased to ~44 wk2026Ch 2.3
18–36 mo+aeroderivative turbine lead time (refurb under 12 mo; some cores quoted to ~243 weeks)2025Ch 3.5
100+ wkMV switchgear lead time; ~128 wk standard HV transformer, ~144 wk GSU-class2025Ch 4.2
IT & equipment averages

GPUs are owner-furnished for a reason; averages hide the tails that bite.

Lead timeFigureAs ofChapter
6–12 moH100/H200 GPU lead times through 2025–2026 — why GPUs are owner-furnished and on allocation2026Ch 2.2
~33–42 weeksJLL global / US average data-center equipment lead time across packages2025Ch 2.3

Why these numbers rule the schedule: the integrated master schedule (Ch 2.1) · the long-lead supply chain (Ch 2.3) · the power-bound era (Ch 16.1).