Chapter 3.3
In this chapter · 6 sections
Power Availability & Power-Cost Structure
Power’s share of lifetime opex depends on whether the denominator includes the GPUs, facility and financing. Underwrite the delivered bill through ramp and curtailment: price, shape, fixed charges and exit terms signed at siting survive the chip purchase.
What you'll decide here
- Whether the candidate site clears the physical power-availability screen — transmission proximity, voltage class, and existing substation headroom — through the utility’s accepted phase-load study alongside the other mandatory gates, because a site that needs a greenfield substation and a new line is a different project on a different schedule than one with bays to spare.
- Which price denominator you are actually underwriting against: an all-in delivered ¢/kWh, or its decomposition into energy (nodal/LMP, including its congestion and loss components), any separate contractual basis adjustment, capacity and demand charges — because fixed floors can raise effective cost as the actual load falls, even while the headline energy price stays unchanged.
- How much curtailment exposure you will accept in exchange for queue speed and a lower energy charge — and whether your workload's goodput economics survive the expected curtailment-hours, because flexible/non-firm service buys value only after lost progress, restart, completion deadlines and continuing fixed charges are priced.
- Who pays for the network upgrades your load triggers — you, via a large-load tariff and minimum-take, or the ratepayer base — because the cost-allocation regime in your jurisdiction can add a fraction of a cent to several ¢/kWh of effective cost and is increasingly the deciding political variable on whether you get to build at all.
- Which power-cost components are fixed at contract signing (and therefore irreversible for the tenor) versus which float with the market (and therefore must fit the owner’s budget and liquidity limits) — because a 15-year asset financed against a merchant energy curve is a fundamentally different risk than one behind a fixed-price PPA.
Chapter 3.2 treated interconnection as a yes/no gate against a schedule: can you get power to this site, and when. Once the answer is yes, the economics turn on what that power actually costs, in what structure, and who bears the cost of the grid you are about to stress. The two questions are separable on purpose. A site can clear the speed-to-power gate and still be uneconomic, because the megawatts arrive at a price, a shape, and a set of curtailment and cost-allocation terms that the GPU fleet cannot earn against.
In Epoch AI’s 2026 1 GW model, energy is the largest operating-cost category; the share depends on what the model includes as opex, especially GPUs, facility cost and financing. Silicon dominates capex; electricity dominates opex. The power-cost structure is therefore the dominant TCO lever still available after the building exists — you cannot re-spec the chips, but with enough foresight at siting you can change the delivered cost of energy by a factor of two or three. What follows works through each fork in the power-cost stack and the dollars that ride on getting it wrong.
Screen one: transmission proximity, voltage class, substation headroom
Before any tariff analysis, a site faces a physical screen that has nothing to do with price and everything to do with what steel is already in the ground. Three variables decide whether a site is powerable on a reasonable schedule at all: transmission proximity, voltage class, and substation headroom. Get these wrong and the cheapest energy market in the country is irrelevant, because the required lines, rights-of-way, equipment and approvals may dominate the project schedule and cost before a single electron arrives.
Transmission proximity is the first cut. A gigawatt-class campus needs a high-voltage transmission tap — typically 230 kV or 345 kV, and increasingly 500/765 kV as backbone projects (ERCOT's statewide ~2,500-mile, ~$33B 765 kV expansion, PJM and SPP build-outs) reach the load. A site adjacent to an existing high-voltage line with spare thermal capacity is a fundamentally different proposition than one that needs miles of new line, every mile of which carries its own permitting, right-of-way acquisition, and 100+-week conductor and structure lead times. The distance to a viable tap is, in practice, a schedule variable, not a geography variable.
Voltage class sets both the equipment you must buy and the losses you will eat. The higher the delivery voltage, the more power you can move per ampere and the lower the I²R losses, but the more expensive and longer-lead the step-down transformers and the larger the customer substation footprint. A 1 GW load taken at 345 kV is an entirely different electrical interface — and a different substation cost — than 200 MW taken at 138 kV. This is an irreversible decision: the voltage class is baked into the substation, the protection scheme, and the interconnection agreement, and you cannot re-pick it mid-life without rebuilding the interface.
Substation headroom is a variable that can change the energization path materially. A utility substation with spare transformer capacity and an open bay can absorb a new large load by adding a feeder; one that is already at its firm rating requires a new transformer bank (~128–208 week lead time; up to ~60 months in constrained markets) or an entirely new substation. The highest-value pre-diligence a developer can do is to map, for every candidate site, the nameplate and firm rating of the serving substation, its current loading, and the queue of other large loads ahead of you for the same headroom. Headroom is a depletable shared resource, and you are rarely the only one shopping for it.
The power-cost stack: decomposing the headline rate
Operators routinely shop on a single number — a delivered ¢/kWh — but that number averages together components that behave very differently under an AI load shape. A defensible power-cost model decomposes the headline rate into four parts, each with its own driver, its own volatility, and its own hedge:
- Energy (the commodity). In organized markets, bus Locational Marginal Price (LMP) is the dispatch primitive; the price payable by load may instead be a load-zone settlement price, zonal LMP, utility tariff, or negotiated retail product. The applicable energy price varies by location, interval, market, and contract. The same MWh can cost a few dollars at a wind-rich West Texas node and a hundred-plus dollars at a congested load center in the same interval.
- Congestion / basis. LMP decomposes into a system energy price plus a congestion component plus a small loss component. Congestion is the value of transmission scarcity between generation and your node, and it is the most under-modeled line in a merchant power plan. A node downstream of a transmission constraint can settle persistently above the hub; a node co-located with stranded generation can settle below it, occasionally negative.
- Capacity. In capacity markets (PJM, ISO-NE, MISO) you pay a separate charge for the resource adequacy your load obligates the system to procure. PJM's capacity auction clearing prices spiked roughly an order of magnitude in 2025–2026 as data-center load tightened the supply-demand balance, turning capacity from a rounding error into a material line item.
- Demand charges. Regulated retail tariffs bill the largest line not on energy consumed but on billing demand: demand-charge rate ($/kW-month) × billing demand (kW), often with a ratchet that holds the charge near the annual peak for months. For a high-load-factor data center this is usually favorable — a flat 90%+ load factor amortizes the demand charge over enormous consumption — but for a spiky or curtailed load it can dominate.
The decomposition matters because two sites with the same delivered ¢/kWh can have completely different risk profiles. One may be 90% energy and 10% congestion (a merchant-exposed, basis-risk-heavy site); the other may be 50% capacity and demand charges (a regulated, schedule-stable site with little hourly exposure but a high floor). Hedging starts from this decomposition — you cannot buy an instrument against a component you have not priced. → PPA structures, basis risk, and the hedging toolkit (CRRs/FTRs, heat-rate hedges) live in Chapter 3.4.
| Cost component | What it prices | Primary driver | Volatility | How it's managed |
|---|---|---|---|---|
| Energy (LMP) | Marginal energy at your bus, per MWh | Fuel + dispatch + your nodal location | High — hourly, can swing 10x+ intraday | Fixed-price or indexed PPA; load-shifting to off-peak (batch) |
| Congestion / basis | Transmission scarcity between generation and your node | Line constraints; queue of generation upstream | High and location-specific; can be negative | Nodal siting; CRRs/FTRs; co-location with generation |
| Capacity | Resource adequacy your load obligates | Reserve margin; capacity-auction clearing | Stepwise — auctions; PJM spiked ~10x in 2025-26 | Demand response participation; curtailable interconnection |
| Demand charge | Monthly peak kW (often ratcheted) | Your peak demand vs your average | Low if load factor is high and flat | High, flat load factor; transient smoothing; peak shaving |
| Transmission / delivery | Use of the grid to deliver to you | Utility tariff; large-load rate class | Low-moderate; set by regulator | Voltage class (higher = lower per-MWh delivery); tariff election |
The main reason an AI data center is a good power customer — and the reason it can sometimes secure rates a flickering industrial load cannot — is its load factor. A facility running training or steady inference at a flat 80–95% of contract demand around the clock is the dream customer for a utility recovering the fixed cost of a substation and a line: it amortizes those fixed charges over the maximum possible consumption, driving the effective ¢/kWh of the delivery and demand components down toward their floor. That amortization lets a high-load-factor data center clear an economic deal on a tariff that would crush a peaky factory. The corollary is a warning: anything that lowers your load factor — curtailment, demand-response events, training-job idle gaps, a half-full hall during ramp — raises your effective per-MWh cost on the fixed components, because the same demand and delivery charges now spread over fewer megawatt-hours. Curtailment costs you the energy you forgo and the fixed charges you keep paying on power you are not drawing.
Scope & caveats
Decide between a component bill and an assumed fully variable $80.0/MWh offer for the same firm service. At the facility revenue meter, assume 10.0 MW contracted capacity, a flat 8.00 MW draw for all 8,760 hours of a non-leap year and the same 8.00 MW monthly demand peak. The component contract has $50.0/MWh energy, already including congestion and losses at that settlement point; $5.00/MWh delivery; $10.0/kW-month demand on max(actual monthly peak, 9.00 MW minimum); and $100,000/year fixed facilities charges. Assume 12 billing months, no ratchet beyond that minimum, zero separate capacity, reactive-power, standby, tax or exit charge, and no interruption, energy-volume floor, credits or additional hedge. The variable offer includes those same services with no minimum or fixed charge. The downside changes only flat draw/peak to 4.00 MW. These teaching contracts isolate the meter, demand floor and ramp mechanisms; neither is an Oregon or AEP tariff or a supplier offer. All prices, MW levels and the facilities charge are exact teaching constants with three-significant-figure display resolution, not supplier estimates. The base/downside draw is below contracted capacity and straddles the calculated offer crossover; the demand minimum exceeds both draws, isolating fixed-cost exposure. A non-leap year, equal monthly peaks and twelve billing months are timing conventions. Zero additional charges and identical firmness define the comparison boundary. Chapter 3.3 owns energy versus demand billing; the AEP source supports testing multiple demand bases, not these assumed rates or minimums.
Build the invoice before comparing its rate. Annual energy in MWh = flat MW × non-leap-year hours. Monthly billing demand = max(actual peak, contractual minimum). Energy and delivery cash each equal MWh × their respective prices; demand cash = billing MW × kW per MW × the kW-month price × billing months. Add fixed facilities cash, then divide the total by energy delivered. Use the unrounded energy and charges throughout; the displayed GWh and money are rounded only at the end.
Scope & caveats
Three-significant-figure display; calculate before rounding. Base energy=8.00 MW×8,760 h≈70.1 GWh/year. Energy cash≈$3.50m; delivery≈$0.350m; demand=max(8.00,9.00) MW×1,000×$10.0/kW-month×12≈$1.08m; facilities=$0.100m. Total≈$5.03m/year, or $71.8/MWh. The variable offer is ≈$5.61m/year, so the component saving is ≈$0.572m. At 4.00 MW, energy≈35.0 GWh; demand plus facilities remains ≈$1.18m. Component cash≈$3.11m ($88.7/MWh), versus ≈$2.80m variable; variable saves ≈$0.304m/year. Under the minimum-demand branch, (80.0−55.0) dollars/MWh×E=1.18 million dollars, so E≈47.2 GWh/year and E/8,760≈5.39 MW, below 9.00 MW as required. Choose variable below that crossover and component above it within the stated common-service boundary.
Select the component contract at the base draw and the variable contract in the lower-draw case. While the demand minimum governs, the crossover is fixed annual demand-and-facilities cash divided by the difference between the variable offer and component energy-plus-delivery price; divide that MWh quantity by year hours to obtain average MW. Confirm the crossover lies below the minimum before using that branch. Curtailing energy does not erase a continuing demand or facilities charge.
AEP Ohio’s DCT explanation supports the distinction between billing-demand tests and energy consumed; these prices and floors are independently assumed. Obtain the operative tariff for a real site. Carry the ramp downside to 2.5 and price PPA exposures in 3.4.
Scope & caveats
All-in average price to ultimate commercial customers; deregulated-supply averages (e.g. Electric Choice ~6.8¢/kWh, Jun 2026) use a narrower cost scope and are not comparable.
Scope & caveats
This is the rental/IaaS denominator (SemiAnalysis, contested). Distinct and much larger is the lab token-revenue side: SemiAnalysis's Tokenomics model (Aug 2026) puts OpenAI/Anthropic API inference at >$100B/GW/year on a GB300 cluster against ~$12B/GW/year of rental cost — a model-derived figure sensitive to utilization and price mix, not an audited disclosure. Do not conflate lab API revenue with IaaS rental in one number.
Scope & caveats
First-order model over 22 balancing authorities using 2016–2024 load histories and constant added load. At 0.5% curtailed annual energy, mean event duration is 2.1 hours; 177 hours per year have some curtailment, distinct from about 44 full-load-equivalent hours. Local network capacity, ramping and ramp-feasible reserves are outside the model.
National modeled potential does not allocate service to a parcel; require the local power-flow/stability study and executable offer.
Nodal pricing, congestion, and the basis-risk trap
In an organized market — ERCOT, PJM, MISO, SPP, CAISO, ISO-NE — energy does not have one price; dispatch has an LMP at every node. A bus LMP is a dispatch primitive, while a load's payable price follows its market and contract — for example, ERCOT typically settles wholesale load at a Load Zone Settlement Point Price, and a retail data center may instead face an REP or utility tariff. Site screening therefore compares the price at the load's actual settlement point or tariff, not an assumed bus LMP; congestion and losses still flow through the applicable pricing chain.
West Texas illustrates the exposure. ERCOT publishes prices at Resource Nodes, Hubs, and Load Zones; a VPPA settled at a resource node and a data center priced at a Load Zone SPP or retail tariff occupy different settlement points, so congestion changes the spread between them. This is locational basis risk: a hedge struck at a hub or resource node does not automatically protect load priced at a zone or tariff, so site screening and hedge design must use the project's actual settlement chain. → the full basis-risk and VPPA-settlement treatment, including negative-settlement stress tests, is in Chapter 3.4; the lender's view of that exposure in Chapter 2.5.
Deep dive: why the cheapest node is rarely the cheapest power
The instinct to chase the lowest LMP node treats nodal price as if it were a fixed property of a location, like land cost. It is instead the output of a dispatch optimization that depends on what generation is online, what transmission is constrained, and what every other load is doing in that interval. A node sits below the hub for one of two reasons, and they have opposite consequences.
Generation-pocket nodes are cheap because abundant local generation cannot all export — the classic West Texas wind case. Site a load here and you absorb the surplus, often at near-zero or negative prices. But this is precisely where curtailment risk concentrates: when the local generation drops or a line trips, the node can spike, and a flexible-interconnection agreement may force you to shed load exactly when you most want to run. You captured cheap energy by accepting correlated curtailment and price risk.
Load-pocket nodes are the inverse — expensive because demand exceeds what local lines can import. A load center behind a constraint settles persistently above the hub, and a new gigawatt of data-center load makes the constraint worse, lifting your own price and everyone else's. Adding load to a load pocket is self-defeating: you raise the price you pay by the act of consuming.
The practitioner's move is to model the distribution of hourly nodal price at the candidate bus across at least a full weather year, not the annual average — because the average flatters a node whose risk lives in the tails. Then decide whether to take that exposure raw (merchant), hedge it with a financial instrument and accept the residual basis (CRRs/FTRs against the hub), or eliminate it with a co-located or behind-the-meter supply that bypasses the nodal market entirely. → instruments and structures in Chapter 3.4; co-located and on-site generation in Chapter 3.5.
Curtailment exposure as a priced lever
The power decision of the 2026 era has moved past "firm grid or not" to how much curtailment you will accept in exchange for queue speed and a lower energy charge. Every major RTO is building a faster interconnection lane for loads that agree to be curtailed: ERCOT's mandatory curtailment / 'kill switch' for large loads interconnecting after the end of 2025, SPP's price-responsive curtailment and non-firm tracks, PJM's non-capacity-backed and interim arrangements, and the FERC flexible-load study concept. Duke’s national estimate is conditional: Duke’s February 11, 2025 study modeled 98 GW of US grid headroom integratable at just 0.5% annual curtailment — about 44 full-load-equivalent hours a year. That is a national modeling result, not an inventory of deliverable capacity at your substation: a site-specific power-flow and stability assessment and an executable service offer are what turn it into megawatts you can energize.
Curtailment is therefore a priced lever, not a binary. The question is whether your workload's goodput economics survive the expected curtailment-hours. A batch-inference or checkpoint-tolerant training fleet can absorb a few hundred curtailment-hours a year by rescheduling work or riding through on storage, paying for the privilege of a faster, cheaper interconnection. An always-on inference business serving an SLA cannot — every curtailed hour is breached revenue, and the cheap non-firm energy is a false economy. Underwrite the cost of the expected curtailment-hours given your workload, netted against the queue-time and energy savings you are buying — the curtailment cap alone tells you neither. → the load-flexibility and grid-services revenue framing lives in Chapter 15.8; curtailable/non-firm interconnection mechanics in Chapter 3.2.
Network upgrade cost allocation: the 'who pays' question
A gigawatt of new load does not arrive on the existing grid for free — it triggers transmission and distribution upgrades, sometimes hundreds of millions of dollars of them. The defining regulatory and political question of 2025–2026 is who pays: the data center that caused the upgrade, or the ratepayer base that did not. This was a footnote five years ago. It is now frequently the deciding variable on whether a project gets approved at all, because rising residential bills in data-center-heavy regions have made cost allocation a live political fight.
The mechanism through which the answer is set is the large-load tariff — a new customer class, now approved in 23+ states, written specifically to push the cost of the buildout onto the loads that cause it. The Oregon POWER Act template is representative and worth memorizing because variants of it are spreading — the Oregon PUC approved PGE’s Schedule 96 under it in May 2026 (Order 26-154, UM 2377): a 20 MW+ threshold defines the class; the large load pays 100% of the distribution-upgrade cost it triggers; minimum generation and transmission demand charges at 90% of contracted system capacity (a take-or-pay floor — you pay for 90% of what you contracted whether you draw it or not) protect the utility against stranded investment if you under-build or leave; 10–30-year contract terms scale with load size, reaching 30 years at 220 MW and above; and a 1¢/kWh surcharge applies above 100 MW of allocated system capacity. These are the PUC template figures (2025 statute; 2026 order) — verify the operative Schedule 96 / UM 2377 sheets and the project service agreement before entering any of them as a bill operand, and note that Pacific Power’s data-center tariff (UE 463) is a separate proceeding. ERCOT's SB6 regime is the Texas analogue, with a 75 MW large-load definition, mandatory curtailment, and a ≥$100,000 screening study fee. Virginia, the largest US market, layered on a flat $0.011/kWh data-center consumption tax effective July 2026.
The consequence for the model is direct and large: these allocation mechanisms can add anywhere from a fraction of a cent to several cents per kWh of effective cost, and the minimum-take floor converts a variable energy bill into a fixed obligation that behaves like debt. A take-or-pay floor means the curtailment savings discussed above are partially illusory — you keep paying the demand floor on power you are not drawing. The 'who pays' regime in your jurisdiction is a first-order input to the power-cost stack and, increasingly, to whether the project clears its social-license gate at all. → the regulatory mechanics and the federal-vs-state collision over large-load interconnection are owned by Chapter 3.2; the macro load-growth and cost-shift narrative in Chapter 16.1.
Scope & caveats
PUC template figure for PGE Schedule 96 under the Oregon POWER Act (HB 3546, 2025); verify the operative Schedule 96 / UM 2377 sheets and the executed service agreement — the component floors, ramp relief and exit charges in that agreement govern the bill. Pacific Power’s data-center tariff (UE 463) is a separate proceeding.
Scope & caveats
PUC template figure for PGE Schedule 96 under the Oregon POWER Act (HB 3546, 2025); verify the operative Schedule 96 / UM 2377 sheets and the executed service agreement before using it as a bill operand. Pacific Power’s data-center tariff (UE 463) is a separate proceeding.
| Allocation regime | Who pays the upgrade | Typical terms | Effect on power cost | Project consequence |
|---|---|---|---|---|
| Legacy / socialized | Ratepayer base (everyone) | Standard tariff; no special class | Lowest direct cost to the operator | Politically unsustainable; driving the backlash and new tariffs |
| Large-load tariff (Oregon POWER Act / PGE Schedule 96) | The large load (cost-causer) | 20 MW+ class; 100% distribution upgrade; 90% min demand; 10–30 yr; 1¢/kWh above 100 MW (PUC template, 2026) | Adds fraction-to-several ¢/kWh; take-or-pay floor | Defensible and durable; converts the energy bill into a debt-like obligation — underwrite ramp and exit terms |
| ERCOT SB6 (Texas) | The large load (75 MW+) | Mandatory curtailment; ≥$100k study fee; 765 kV backbone | Lower energy; curtailment risk priced in | Faster queue if flexible; SLA-incompatible for firm inference |
| Consumption tax (Virginia) | The data center (flat per-kWh) | $0.011/kWh on all DC electricity from Jul 2026 | Adds ~1.1¢/kWh flat to every MWh | Predictable but unavoidable; erodes the low-rate advantage |
Carry the delivered bill into total project cost
After the chips are bought, power is the largest controllable variable in the lifetime cost of the asset. Silicon dominates capex and is essentially fixed at procurement — you buy the GPUs at market and depreciate them on a contested schedule (→ Chapter 1.8). The building shell is a small and slow-moving line. But energy — the largest operating category in the cited Epoch model, with its stated denominator — is the cost you can still move by a factor of two or three through decisions made at siting: which node, which voltage class, which tariff, how much curtailment, behind-the-meter or grid.
The leverage is starkest netted against the revenue the asset earns. Against that topline (Chapter 1.8's revenue-per-GW figure), a mis-structured energy bill can run to many hundreds of millions a year. A 2¢/kWh difference in delivered power cost — entirely achievable between a well-sited, well-hedged location and a poorly-structured one — is on the order of $175M/yr on a 1 GW facility at 100% load factor. No engineering efficiency in the rest of this guide moves that much money, which is why the screen runs availability first, structure second, and only then everything else.
Sort the power-cost components by reversibility, the same way Chapter 1.1 sorted the scoping decisions. The irreversible components are fixed at contract: the voltage class and substation interface, the large-load tariff election and its take-or-pay floor, the contract tenor, and a fixed-price PPA's strike. The reversible components float and must be hedged or actively managed: the merchant energy and congestion exposure, the capacity-auction outcome, and the curtailment-hours you actually incur. A 15-year asset financed against a merchant energy curve is a far riskier instrument than one behind a matched-tenor fixed-price supply; which of the two you are is decided here, and the lenders in Chapter 2.5 will price the difference ruthlessly.
Deep dive: the power-tenor-vs-GPU-life matching problem, previewed
A further power-cost decision is one of duration matching, and it sits at the seam between this chapter and the next. A large-load tariff or a fixed-price PPA often runs 10–30 years — the term the utility or generator needs to recover the substation, line, or plant it built for you. The GPU fleet inside the building is tested against a contested 2–3-year frontier-economic bear case and published 4–6-year useful-life estimates, alongside 5–6-year book policies (→ Chapter 1.8). The mismatch is structural: you are signing a multi-decade fixed power obligation against a revenue stream generated by hardware that turns over four-to-ten times within that obligation.
The consequence is a real risk, not an accounting curiosity. If token prices deflate, if your workload mix shifts, or if a refresh strands part of the hall, the power obligation does not shrink — the take-or-pay floor keeps billing whether or not the GPUs behind it are earning. Conversely, a too-short power contract leaves you re-exposed to a merchant market that may have moved against you precisely when your fleet is most valuable. The matching problem has no free answer; it is a deliberate choice about which tenor of risk you would rather carry — fixed-price certainty that may outlive the workload, or merchant flexibility that may spike. The structures that manage this seam — physical vs virtual PPAs, indexed vs fixed, the firming and co-location options — are the subject of Chapter 3.4, and the downside stress tests of getting it wrong are run in Chapter 1.8.
Cite this chapter
Fehn, J. (2026). Power Availability & Power-Cost Structure (Chapter 3.3). The Definitive Guide to AI Data Centers. https://aidatacenterguide.com/part-3-site-selection-power-procurement-and-permitting/3-3-power-availability-and-power-cost-structure (accessed 2026-09-29).
@misc{aidc-3-3,
author = {Fehn, Jacob},
title = {Power Availability & Power-Cost Structure (Chapter 3.3)},
howpublished = {The Definitive Guide to AI Data Centers},
year = {2026},
url = {https://aidatacenterguide.com/part-3-site-selection-power-procurement-and-permitting/3-3-power-availability-and-power-cost-structure},
note = {Accessed 2026-09-29}
}