time-to-power: greenfield self-build vs wholesale colo (live 50k+ GPU cluster) vs neocloud

~24–36 mo once power is secured (queue adds 4–7 yr in dense hubs) / ~6–12 mo fit-out / days–weeksobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeEach leg is gated differently: queue position and tariff process (self-build), provider capacity + fit-out (colo), available inventory (neocloud).
Caveat2026 practitioner bands, not commitments — the executed tariff, studies and agreements set any given project's schedule.
As of2026-08-26
SourceJLL, 2026 Global Data Center Outlook · Interconnection >4 yr average, ~7 yr Northern Virginia; ~2 yr construction
DerivationSelf-build: ~24–36 mo construction once power is secured (CBRE 2026: 18–24 mo groundbreaking-to-commissioning for sub-500 MW; SemiAnalysis practitioner band) — the grid queue in front of it averages >4 yr in major markets and ~7 yr in Northern Virginia (JLL 2026 Outlook), which is why queue position, not construction, gates greenfield. Wholesale colo: ~6–12 mo fit-out of an energized shell (xAI Colossus's 122-day build is the compressed extreme; CBRE reports preleased delivery beyond 12 mo for new shells). Neocloud: days–weeks when capacity exists; reserved capacity books months ahead.
Reviewchecking…review by 2026-11-26 · standard cadence
Recorded changeslast 2026-08-26 · 4 revisions tracked
Claim idtime-to-power-greenfield-self-build-vs