Illustrative 150 MW facility transformer sizing: three units, one unavailable, 0.95 power factor, 0.95 site factor and 10% planning margin

About 91 MVA per unit; select above the exact boundderived

Value kindderived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method.
ScopeIllustrative facility input load, not IT load. A 100 MVA candidate passes this capacity screen; 80 MVA fails under the stated derating.
As of2026-09
SourceGuide derivation — illustrative capacity screen dated September 8, 2026; Chapter 4.4, not a typical OEM rating. · Chapter 4.4: 150 MW × 1.10 / (0.95 PF × 0.95 site factor × 2 surviving units).
Derivation150×1.10/(0.95×0.95×2)=91.412742... MVA; about 91 MVA is display only, not a qualifying nameplate. Three 100 MVA candidates pass, 80 MVA fails. Raw-load crossover 2×100×0.95×0.95/1.10=164.090909... MW; display about 160 MW, use full inequality. At assumed 170 MW the candidate fails.
Reviewchecking…review by 2027-03-05 · standard cadence
Recorded changeslast 2026-09-16 · 3 revisions tracked
Claim idtypical-hv-mv-transformer-unit-n-1-to-serve-150

Where the guide uses it

← Full numbers register — every date-stamped figure in the guide, with revision history.