Reported U.S. average switchgear lead time, Wood Mackenzie Q2 2025; voltage class not specified
~44 wkobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | A historical U.S. benchmark for the report's Switchgear category. It is neither an MV-only average nor a current supplier quote; HV equipment has its own benchmark. |
| As of | 2025-Q2 |
| Source | Wood Mackenzie / American Clean Power, Making the Connection, September 2025 · printed p. 6 (PDF page 5), Equipment lead times remain volatile |
| Review | checking…review by 2027-01-31 · fast cadence |
| Recorded changes | last 2026-10-13 · 4 revisions tracked |
| Claim id | mv-switchgear-lead-time-128-wk-standard-hv |