schedule compression of highly modular vs conventional builds (24–36 mo → ~16–20 mo)
30–50%observed
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | modular schedule compression |
| As of | 2026 |
| Source | DCD; Cadence; Data Center Knowledge (2026) · Modular construction discussion: 30–50% schedule reduction, compressing 24–36 months to approximately 16–20 months |