schedule compression of highly modular vs conventional builds (24–36 mo → ~16–20 mo)

30–50%observed

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
Scopemodular schedule compression
As of2026
SourceDCD; Cadence; Data Center Knowledge (2026) · Modular construction discussion: 30–50% schedule reduction, compressing 24–36 months to approximately 16–20 months
Reviewchecking…review by 2026-11-23 · standard cadence
Recorded changeslast 2026-06-29
Claim idschedule-compression-of-highly-modular-vs