nVent RDHX PRO active 800 mm rear door, rated capacity at 14 °C supply water and 24 °C supply air
78 kW at 14 °C water / 24 °C airobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Caveat | Door capacity depends on water temperature and airflow. The same active door is rated 44 kW at 24 °C water and 27 °C air, and its table assumes 6.0 m³/h of water and 10,000 m³/h of air for the 750–800 mm variant. Passive doors carry less and are rated per model: nVent's passive 800 mm RDHX PRO is 38 kW at 14 °C water/24 °C air and 34 kW at 24 °C/27 °C. The datasheet prints no publication day. Get an OEM quotation for the door, interfaces, CDU allocation and installation. |
| As of | nVent datasheet ©2025; checked 2026-10-14 |
| Source | nVent RDHX PRO active, SCHROFF-SPEC-N00647-RDHXPRO-EN |
| Review | checking…review by 2027-04-01 · standard cadence |
| Recorded changes | last 2026-10-14 · 5 revisions tracked |
| Claim id | rdhx-capacity-per-rack-passive-15-30-kw-active |