PJM generation EIT study and readiness deposits under the tariff accepted June 9, 2026

$500k study + $15k/MWobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeEligible new or uprated generation offering at least 250 MW accredited UCAP; study deposit $500,000, readiness deposit $15,000/MW. This is not a campus load-service application schedule.
CaveatTemporary generation track; host-utility load service has separate study, service and security obligations.
As of2026-06-09
SourceFERC June 9, 2026 order, ER26-1563-000; accepted Part X effective July 31, 2026. · Order discussion of deposits and Appendix A, Part X effective date.
Reviewchecking…review by 2026-12-01 · fast cadence
Recorded changeslast 2026-09-16 · 3 revisions tracked
Claim idpjm-interconnection-deposits-committed-before