PJM generation EIT study and readiness deposits under the tariff accepted June 9, 2026
$500k study + $15k/MWobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | Eligible new or uprated generation offering at least 250 MW accredited UCAP; study deposit $500,000, readiness deposit $15,000/MW. This is not a campus load-service application schedule. |
| Caveat | Temporary generation track; host-utility load service has separate study, service and security obligations. |
| As of | 2026-06-09 |
| Source | FERC June 9, 2026 order, ER26-1563-000; accepted Part X effective July 31, 2026. · Order discussion of deposits and Appendix A, Part X effective date. |
| Review | checking…review by 2026-12-01 · fast cadence |
| Recorded changes | last 2026-09-16 · 3 revisions tracked |
| Claim id | pjm-interconnection-deposits-committed-before |