PJM generator interconnection: application-to-commercial-operation timeline (vs <2 yr in 2008); a generation statistic, not a large-load service timeline
>8 yrobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | RMI's series measures bringing new generating capacity online in PJM. It is supply-side context for a load project; it does not measure how long a data-center load request takes to be served. |
| As of | 2025 |
| Source | RMI / PJM filings · Opening discussion and Exhibit 2: average application-to-commercial-operation time increased from under two years in 2008 to over eight years in 2025. |
| Review | checking…review by 2026-08-27 · standard cadence |
| Recorded changes | last 2026-07-07 |
| Claim id | pjm-application-to-commercial-operation |
Where the guide uses it
← Full numbers register — every date-stamped figure in the guide, with revision history.