The Chapter 4.1 guide fixture compares four AC packages with three integrated MV/DC packages through the final converter output.

4 → 3 packages; ≈82% AC / ≈87% DC; 100 MW final output; 415 VAC / 800 VDC alternative branchesderived

Value kindderived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method.
ScopeAssumed screening case; use the full-precision equations for comparisons, not rounded display limits. Actual equipment qualification remains separate.
As of2026-09-08
SourceGuide derivation — Guide AC assumptions, September 8, 2026; Chapter 4.1 stated-assumption case. · Chapter 4.1 — Illustrative — stated assumptions
DerivationAC=.99×.94×.96×.92=.82190592; DC=.98×.965×.92=.870044. Report about 82%/87%. 100 MW final output; source input 100/eta. No prototype measurement or route/auxiliary advantage credited.
Reviewchecking…cadence-derived review 2027-01-06 · standard cadence
Recorded changesnone recorded
Claim idpart4-conversion-ledger