SPP CHILLS is conditional non-firm service with a maximum seven-year term under the described tariff

Maximum 7-year conditional non-firm termobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeProduct term and eligibility under the applicable tariff, not a study or construction duration and not HILLGA generation assessment.
As of2026-06-18
SourceFERC — Order 195 FERC ¶61,213, issued June 18, 2026, paragraph 17 / printed page 16; describes the June 5 CHILLS acceptance. · 195 FERC ¶61,213, June 18, 2026, discussion of SPP CHILLS
Reviewchecking…review by 2026-12-05 · standard cadence
Recorded changeslast 2026-09-16
Claim idpart3-spp-chills-service-limit