The Definitive Guide toAI Data Centers
Ask the GuideAboutAccount
Guide › Numbers register › Claim

CFS targets grid electricity from ARC in the early 2030s

Early 2030sforecast

Value kindforecast — Forecasts are time-bound outlooks, not specifications; test decisions across plausible scenarios.
ScopeCompany target for the generating plant. SPARC is the demonstration machine; no firm 2030 data-center supply is established.
As of2026-08-05
SourceCommonwealth Fusion Systems, SPARC progress and ARC deployment update, 5 August 2026. · SPARC/ARC distinction and Fall Line Fusion Power Station deployment paragraph
Reviewchecking…review by 2026-12-05 · standard cadence
Recorded changeslast 2026-09-16
Claim idpart16-cfs-arc-grid-target

Where the guide uses it

← Full numbers register — every date-stamped figure in the guide, with revision history.