Illustrative one-crew power/CDU/shared-control/restart-all model

about 9.9 h/year downtime; 90.8% goodputmodeled

Value kindmodeled — Interpret this value according to its displayed kind, scope, source, and as-of date.
ScopeAll ledger and mitigation rates, timing, 1024-GPU population, annual costs and $2.0/GPU-hour value are assumed. Prices: 200000 fast, 10000 control, 50000 fourth CDU, 25000 repair, 150000 third path, 210000 combined USD/year. 2000 windows, seeds 120500+i.
As of2026-09
SourceNIST supplies independent r-out-of-n assumptions only. Guide finite-crew and event-process implementation from synthetic inputs; no field calibration or NIST procurement recommendation.
DerivationIndependent pool availability from one-crew stationary weights; full retained-checkpoint progress from the embedded standard-library event simulation. ΔG*1024*8760*2 minus annual cost supplies the economic screen.
Reviewchecking…review by 2027-09-05 · standard cadence
Recorded changeslast 2026-09-16
Claim idpart12-reliability-model-case

Where the guide uses it