Illustrative ten-year equal-load power-package comparison
Cost tie: about $3.6m each; required operating states decidederived
| Value kind | derived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method. |
|---|---|
| Scope | All equipment, cost, load, time and operational inputs are stated scenario assumptions, not quotes or Tier cost ratios. Exact totals of USD 3.600m and 3.625m are a practical cost tie; the required operating states decide. USD 50,000 is the distributed-only addition’s arithmetic crossover, not a procurement margin. |
| As of | 2026-09 |
| Source | Guide derivation; inputs are stated assumptions · Worked power package: inputs, BOM, state matrix and decision |
| Derivation | Exact illustrative budget: 2*1200000+200000+100000+100000+10*80000=3600000; 4*450000+350000+150000+150000+75000+10*110000=3625000; distributed-only addition crossover=50000. Method source supports topology boundaries only; all prices are assumed. |
| Review | checking…review by 2027-09-05 · standard cadence |
| Recorded changes | last 2026-09-16 |
| Claim id | part12-power-package-case |