AWS use1-az4 cooling-plant incident (7 May 2026): simultaneous chiller failures in one data hall; Coinbase core-service disruption

7 May 2026; roughly 8 hours of core-service disruption at Coinbaseobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeCoinbase's account of simultaneous chiller failures in one AWS data hall and the ensuing application outage. Service duration is Coinbase's, not the duration of chiller failure.
As of2026-05-08
SourceCoinbase engineering blog, 'A postmortem of our May 7, 2026 outage' (1 June 2026)
Reviewchecking…review by 2027-06-01 · slow cadence
Recorded changeslast 2026-10-25
Claim idp5-aws-use1-az4-cooling-incident-2026