Lenovo GB300 NVL72 required rack water flow by supply temperature (W45-rated rack)

89 L/min at 35 °C supply (59 L/min at 25 °C; 177 L/min at 45 °C)observed

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopePublished per-rack flow requirement at the named supply temperatures; the ~20 K rise the 35 °C row implies for the liquid share of 135 kW is the guide’s arithmetic, not a Lenovo figure.
As of2026-08-30
SourceLenovo Press, Lenovo NVIDIA GB300 NVL72 Rack Scale AI product guide (LP2357), updated 30 August 2026; required rack flow 59 / 71 / 89 / 119 / 177 LPM at 25 / 30 / 35 / 40 / 45 °C fluid supply, allowable inlet up to 45 °C (ASHRAE W45), 135 kW rack TDP with about 90 % of heat to liquid.
Reviewchecking…review by 2027-03-08 · standard cadence
Recorded changeslast 2026-09-16
Claim idp2b-5-11-lenovo-gb300-nvl72-fws-flow

Where the guide uses it

← Full numbers register — every date-stamped figure in the guide, with revision history.