FERC order in Docket RD26-7-000 (issued July 16, 2026) directs NERC to file Phase I computational-load Reliability Standards and registry-criteria revisions by December 31, 2026 and a Phase II standards workplan by March 1, 2027

Dec 31, 2026observed

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeA filing deadline directed to NERC under FPA §215(d)(5) and §215(f), not an operator compliance date; Phase II workplan due March 1, 2027; verify the operative filing and any Commission extension before fixing settings.
As of2026-07-16
SourceFederal Energy Regulatory Commission, Order Directing NERC to File Reliability Standard(s) Pertaining to Computational Load Integration, Docket No. RD26-7-000, 196 FERC ¶ 61,031, issued July 16, 2026; directs a filing by December 31, 2026 and a Phase II workplan informational filing by March 1, 2027. · Order p. 1 (directives) and ordering paragraphs (A)–(C), pp. 6–7
Reviewchecking…review by 2027-03-08 · standard cadence
Recorded changeslast 2026-09-16
Claim idp2b-4-10-ferc-rd26-phase1-deadline