GB200 NVL72 heat split (HPE) — removed by liquid vs left on air per rack (~132 kW total)

~115 / ~17 kWobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
CaveatHPE GB200-specific. Keep separate from the GB300 NVL72 split: Lenovo Press LP2357 puts GB300 on ~90% liquid / ~10% air — roughly 13.5 kW on air at 135 kW rack TDP and ~15.5 kW at the ~155 kW peak, with the NVLink switch trays moved fully to liquid. Size a residual-air path from the rack you actually name.
As of2025
SourceHPE QuickSpecs (OEM 115/17 split); 132 kW all-in Vertiv/NVIDIA + 451 Research · Advanced Direct Liquid Cooling specification; 132 kW nominal rack TDP split into 115 kW liquid-cooled and 17 kW air-cooled
Reviewchecking…review by 2026-08-13 · standard cadence
Recorded changeslast 2026-07-07 · 2 revisions tracked
Claim idnvl72-heat-split-removed-by-liquid-vs-left-on