MV switchgear lead time (5–38 kV, data-center class) — eased to ~26–32 wk in early 2025, re-tightened on AI demand; some quotes 40–80 wk

~44–65 wkobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
As of2026
SourceCPM Pros (T&T 2025–26 context); VAWN index 44 wk avg (2026-06); Build.inc 40–65 wk (2026); DEI Power (2026-05); GEP (2025-01)
Reviewchecking…review by 2026-08-26 · fast cadence
Recorded changeslast 2026-07-12 · 2 revisions tracked
Claim idmv-switchgear-lead-time-5-38-kv-data-center