average MV-class switchgear lead time (Wood Mackenzie Q2 2025); HV breakers and GIS run far longer — see the HV switchgear claim
~44 wkobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | U.S. 2025 Q2 averages. Transformer categories are based on transformer type, not voltage. |
| As of | 2026 |
| Source | Wood Mackenzie / American Clean Power (Making the Connection); corroborated by VAWN electrical lead-time index (~44 wk avg, 2026-06) · Report page 6, “Equipment lead times remain volatile” chart and commentary |
| Review | checking…review by 2026-09-14 · fast cadence |
| Recorded changes | last 2026-07-21 · 3 revisions tracked |
| Claim id | mv-switchgear-lead-time-128-wk-standard-hv |