MV cable lead time — standard copper MV often stocked domestically, LSZH builds ~10–12 wk; rarely the long pole, but a hyperscale campus consumes 20–50 miles and copper price is the real exposure (distributor-reported, single source)

≤12 wkobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
As of2026
SourceDistributorWire (2026, distributor-reported)
Reviewchecking…review by 2026-09-21 · fast cadence
Recorded changeslast 2026-07-12
Claim idmv-cable-lead-time-standard-copper-mv-often