sustained data-center load step at the third voltage depression in the July 10, 2024 event; remained off for hours

~1.26 GW sustained stepobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeSustained step at the third voltage depression; distinct from roughly 1,500 MW total reduction across the disturbance sequence. This was not a documented cyberattack.
As ofEvent 10 July 2024; report observation date not implied
SourceNERC Incident Review — Considering Simultaneous Voltage-Sensitive Load Reductions
Reviewchecking…review by 2026-09-09 · standard cadence
Recorded changeslast 2026-09-16 · 3 revisions tracked
Claim idload-shed-in-a-single-virginia-event-the