large LV switchboard lead time (1,200 A+) — commodity gear back to 6–10 wk; corroborated by VAWN (switchboards 32–41 wk, LV switchgear 54 wk, 2026-06); engineered draw-out quoted to 70–80 wk

~35–62 wkobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
As of2026-05
SourceDEI Power (2026-05); VAWN electrical lead-time index (2026-06)
Reviewchecking…review by 2026-09-20 · fast cadence
Recorded changeslast 2026-07-12
Claim idlarge-lv-switchboard-lead-time-1-200-a