Large multi-rack GPU program, agreement to commissioned capacity — observed 2025–26 programs run ~6–12 mo: IREN–Dell $1.6B air-cooled Blackwell (signed 2026-05-26, commissioning early 2027, ~7–10 mo); Crusoe MI355X ~3–6 mo; Nebius–Meta capacity ~9–12 mo
~6–12 moobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | multi-rack programs on existing powered sites |
| Caveat | Program duration includes site work, integration and commissioning — not the per-rack hardware clock; priority customers sit at the fast end. |
| As of | 2026-07 |
| Source | SEC 8-K / press: IREN–Dell purchase agreement (2026-05-26), commissioning target early 2027; Crusoe MI355X announcement-to-service (2025-06-12); Nebius–Meta agreement (2026-03-16), capacity early 2027 |
| Review | checking…review by 2026-09-18 · fast cadence |
| Recorded changes | none recorded |
| Claim id | large-gpu-program-order-to-online |
Where the guide uses it
Not quoted in a chapter yet; it is kept in the curated register.
← Full numbers register — every date-stamped figure in the guide, with revision history.