large 3-phase UPS lead time (data-center class) — spread is wide by vendor and configuration; direct procurement cut one 32-wk quote to 10
~40–72 wkobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| As of | 2026 |
| Source | CPM Pros; DPR Construction Q2 2025; Core Scientific FY2025 10-K (critical electrical/cooling 12–18+ mo) |
| Review | checking…review by 2026-09-03 · fast cadence |
| Recorded changes | last 2026-07-12 |
| Claim id | large-3-phase-ups-lead-time-data-center-class |