HV switchgear & circuit-breaker lead time — HV breakers ~100–155 wk with little improvement reported since the ~151-wk late-2023 peak; HV GIS and full substations 3–5 years; MV eased separately
~100–155 wkobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| As of | 2025-11 |
| Source | Duke Nicholas Institute / Wood Mackenzie via The Conversation (2025-11); Build.inc (2026) |
| Review | checking…review by 2026-08-28 · fast cadence |
| Recorded changes | last 2026-07-12 |
| Claim id | hv-switchgear-and-circuit-breaker-lead-time-hv |