Balance the screening stations with the installation crews — stated inputs

72 racks × 16 links/rack; 2 modules/link; screening pass fraction 95%; 4 stations × 32 modules/batch, 2 h/batch, 8 h/day; install 0.25 crew-h/link; rework 10%; 6 productive h/crew-day; compare 4 vs 6 crews; release test 1 day; deadline 10 floor-work days.modeled

Value kindmodeled — Interpret this value according to its displayed kind, scope, source, and as-of date.
ScopeExact link counts; unsupported yield, station and crew budgets. Rationale is in the opening callout; Chapters 6.6 and 2.1 own route validation and scheduling.
As of2026-09
SourceFluke Networks, fiber inspection and testing guidance — method reference; guide-authored hypothetical scenario September 8, 2026. No supplier quote or test measurement.
DerivationExact teaching assumptions chosen to expose the stated constraint and its reversal; not estimates of market prices or actual equipment.
Reviewchecking…review by 2027-03-08 · standard cadence
Recorded changeslast 2026-09-16
Claim idguide2-t29-7-15-inputs