Balance the screening stations with the installation crews — stated inputs
72 racks × 16 links/rack; 2 modules/link; screening pass fraction 95%; 4 stations × 32 modules/batch, 2 h/batch, 8 h/day; install 0.25 crew-h/link; rework 10%; 6 productive h/crew-day; compare 4 vs 6 crews; release test 1 day; deadline 10 floor-work days.modeled
| Value kind | modeled — Interpret this value according to its displayed kind, scope, source, and as-of date. |
|---|---|
| Scope | Exact link counts; unsupported yield, station and crew budgets. Rationale is in the opening callout; Chapters 6.6 and 2.1 own route validation and scheduling. |
| As of | 2026-09 |
| Source | Fluke Networks, fiber inspection and testing guidance — method reference; guide-authored hypothetical scenario September 8, 2026. No supplier quote or test measurement. |
| Derivation | Exact teaching assumptions chosen to expose the stated constraint and its reversal; not estimates of market prices or actual equipment. |
| Review | checking…review by 2027-03-08 · standard cadence |
| Recorded changes | last 2026-09-16 |
| Claim id | guide2-t29-7-15-inputs |