Release the rack interface schedule only when every service fits — conditional result

HOLD: 2.0 kW room-air deficit and 0.10 m service deficit. Nominal week 14 is viable only if both interfaces are ready by week 12.derived

Value kindderived — Derived values are guide calculations; their result is only as fixed as the stated inputs, scope, and method.
ScopeElectrical margin = 132−120 = 12 kW; liquid-duty margin = 120−100 = 20 kW; room-air deficit = 20−18 = 2.0 kW. Coolant rise = 100 kW/(2.0 kg/s × 4.18 kJ/(kg·K)) = about 12 K, so return is about 52°C, below 55°C at the assumed flow. Rear-service deficit = 0.90−0.80 = 0.10 m. The nominal release is max(9,11,10,12) + 2 = week 14, but air and access failures block it. Both must be corrected by week 12 for the two-week test to finish by week 14; correcting them in week 15 instead gives week 17.
As of2026-09
SourceOpen Compute Project Open Rack specifications — method reference; guide-authored hypothetical scenario September 8, 2026. No supplier quote or test measurement.
DerivationElectrical margin = 132−120 = 12 kW; liquid-duty margin = 120−100 = 20 kW; room-air deficit = 20−18 = 2.0 kW. Coolant rise = 100 kW/(2.0 kg/s × 4.18 kJ/(kg·K)) = about 12 K, so return is about 52°C, below 55°C at the assumed flow. Rear-service deficit = 0.90−0.80 = 0.10 m. The nominal release is max(9,11,10,12) + 2 = week 14, but air and access failures block it. Both must be corrected by week 12 for the two-week test to finish by week 14; correcting them in week 15 instead gives week 17.
Reviewchecking…review by 2027-03-08 · standard cadence
Recorded changeslast 2026-09-16
Claim idguide2-t29-7-13-result