Assumed facility-meter bill through a demand-floor ramp — stated inputs

10.0 MW contract; 8.00 MW flat draw (4.00 MW downside); $50.0/MWh energy + $5.00/MWh delivery; $10.0/kW-month on max(peak, 9.00 MW); $0.100m/year facilities; $80.0/MWh variable offer.modeled

Value kindmodeled — Interpret this value according to its displayed kind, scope, source, and as-of date.
ScopeDecide between a component bill and an assumed fully variable $80.0/MWh offer for the same firm service. At the facility revenue meter, assume 10.0 MW contracted capacity, a flat 8.00 MW draw for all 8,760 hours of a non-leap year and the same 8.00 MW monthly demand peak. The component contract has $50.0/MWh energy, already including congestion and losses at that settlement point; $5.00/MWh delivery; $10.0/kW-month demand on max(actual monthly peak, 9.00 MW minimum); and $100,000/year fixed facilities charges. Assume 12 billing months, no ratchet beyond that minimum, zero separate capacity, reactive-power, standby, tax or exit charge, and no interruption, energy-volume floor, credits or additional hedge. The variable offer includes those same services with no minimum or fixed charge. The downside changes only flat draw/peak to 4.00 MW. These teaching contracts isolate the meter, demand floor and ramp mechanisms; neither is an Oregon or AEP tariff or a supplier offer. All prices, MW levels and the facilities charge are exact teaching constants with three-significant-figure display resolution, not supplier estimates. The base/downside draw is below contracted capacity and straddles the calculated offer crossover; the demand minimum exceeds both draws, isolating fixed-cost exposure. A non-leap year, equal monthly peaks and twelve billing months are timing conventions. Zero additional charges and identical firmness define the comparison boundary. Chapter 3.3 owns energy versus demand billing; the AEP source supports testing multiple demand bases, not these assumed rates or minimums.
As of2026-09
SourceAEP Ohio — method reference; scenario authored September 8, 2026. Assumed inputs are not publisher observations.
DerivationExact hypothetical inputs; arithmetic is in the paired result claim.
Reviewchecking…review by 2027-03-08 · standard cadence
Recorded changeslast 2026-09-16
Claim idguide2-t26-delivered-bill-inputs