Illustrative 10.7 decision: 120 s recovery; about 21 GPU-minutes lost/recovered

120 s recovery; about 21 GPU-minutes lost/recoveredmodeled

Value kindmodeled — Interpret this value according to its displayed kind, scope, source, and as-of date.
ScopeAll case inputs and traces are assumed, with their rationale/bounds stated in the case. No provider performance, actual incident, procurement approval or achieved security level is asserted.
As of2026-09-08
SourceGuide, independently constructed teaching case, 8 September 2026; linked primary reference supplies the method, not the synthetic observations. · Chapter 10.7, Illustrative — stated assumptions
DerivationRecovery=20+10+20+40+30=120 s. Equivalent lost/recovery capacity=8×(120+40)/60=21.333 GPU-minutes, rounded about 21. A 60 s allocation delay gives 180 s, beyond the 150 s assumed RTO.
Reviewchecking…review by 2027-03-08 · standard cadence
Recorded changesnone recorded
Claim idguide2-t210-recovery