Illustrative facility power-chain allowance and subtotal at about 220 MW
$10–15M/MW; about $2.2–3.3Bestimate
| Value kind | estimate — Interpret this value according to its displayed kind, scope, source, and as-of date. |
|---|---|
| Scope | Guide allowance; exclude shell and cooling (Chapter 4.1). |
| As of | 2026-09-08 |
| Source | Guide derivation from explicitly assumed unit-price and capacity sensitivities; these are illustrative allowances, not observed quotes. · Appendix B, “Illustrative — stated assumptions” and component BOM. Facility power-chain allowance at the unrounded 223.0272 MW operating point; exclude shell and cooling (Chapter 4.1). See the claim derivation for operands and rounding. |
| Derivation | Nominal IT = 1,408 × 132/1,000 = 185.856 MW. Assumed PUE 1.2 gives 223.0272 MW. Apply assumed $10–15M/facility MW to the unrounded product: $2.230272–3.345408B; display two significant figures. |
| Review | checking…review by 2026-10-08 · fast cadence |
| Recorded changes | last 2026-09-16 |
| Claim id | guide2-b-power-chain-cost-scenario |