The Definitive Guide toAI Data Centers
Ask the GuideAboutAccount
Guide › Numbers register › Claim

Illustrative hot-storage allowance and subtotal for 198 PB usable

$0.20–0.40/GB; about $40–80Mestimate

Value kindestimate — Interpret this value according to its displayed kind, scope, source, and as-of date.
ScopeGuide allowance, decimal usable GB (Chapters 9.6/9.8).
As of2026-09-08
SourceGuide derivation from explicitly assumed unit-price and capacity sensitivities; these are illustrative allowances, not observed quotes. · Appendix B, “Illustrative — stated assumptions” and component BOM. 198 PB decimal usable hot-storage allowance and subtotal (Chapters 9.6/9.8). See the claim derivation for operands and rounding.
DerivationAssume 2 PB usable per 1,024 GPU packages: 101,376/1,024 = 99; 99 × 2 PB = 198 PB = 198,000,000 decimal GB. Multiply by assumed $0.20–0.40/usable GB = $39.6–79.2M; display one significant figure because capacity is approximate.
Reviewchecking…review by 2026-10-08 · fast cadence
Recorded changeslast 2026-09-16
Claim idguide2-b-flash-cost-scenario

Where the guide uses it

← Full numbers register — every date-stamped figure in the guide, with revision history.