Illustrative cooling-plant allowance excluding the separately counted CDUs
$3–5M/IT MW; about $0.6–0.9Bestimate
| Value kind | estimate — Interpret this value according to its displayed kind, scope, source, and as-of date. |
|---|---|
| Scope | Guide allowance; exclude the 235 CDUs and shell (Chapter 5.8). |
| As of | 2026-09-08 |
| Source | Guide derivation from explicitly assumed unit-price and capacity sensitivities; these are illustrative allowances, not observed quotes. · Appendix B, “Illustrative — stated assumptions” and component BOM. Cooling-plant allowance and subtotal; exclude the separately counted 235 CDUs (Chapter 5.8). See the claim derivation for operands and rounding. |
| Derivation | 185.856 MW nominal IT × assumed $3–5M/IT MW = $0.557568–0.92928B; display one significant figure. |
| Review | checking…review by 2026-10-08 · fast cadence |
| Recorded changes | last 2026-09-16 |
| Claim id | guide2-b-cooling-cost-scenario |