GB300 NVL72 rack-scale system order-to-delivery for a non-framework buyer via OEM/integrator — accepted order with a confirmed build slot to dock. Integrator quotes 8–12 wk with a named slot; July 2026 channel sheets 14–24 wk; budget 12–24 wk

~12–24 wkobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
Scopesingle-rack accepted orders; excludes facility prep (~4–6 wk) and program-scale deployment
CaveatEditorial planning range from public channel quotes, not an OEM statistic — a written allocation/ship slot supersedes it. Custom CDU/network BOM and validation push the top of the range; multi-rack programs run ~6–12 mo agreement-to-commissioned.
As of2026-07
SourceiFactory GB300 deployment guide (2026-05): 8–12 wk rack + 4–6 wk facility prep; Haink channel availability sheet (2026-07): B300/GB300 14–24 wk; cross-checked against IREN–Dell $1.6B air-cooled Blackwell program (SEC 8-K 2026-05-26, commissioning target early 2027)
Reviewchecking…review by 2026-09-18 · fast cadence
Recorded changesnone recorded
Claim idgb300-nvl72-rack-system-order-to-delivery