Lenovo NVIDIA GB300 NVL72 rack: nominal TDP and workload-dependent peak
135 kW nominal TDP / up to 155 kW peakobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | One named Lenovo product record. These are distinct operating quantities, not a single scalar or a project electrical design rating. |
| Caveat | Qualify the purchased configuration and transient envelope. The separate NVIDIA reference architecture figure of 142 kW is not a Lenovo design provision. |
| As of | 2026-08 |
| Source | Lenovo Press LP2357 product guide, updated 2026-08-30. · Key features: rack power and air/liquid heat capture; 135 kW TDP, up to 155 kW peak depending on workload and EDP behavior. |
| Review | checking…review by 2026-12-05 · standard cadence |
| Recorded changes | last 2026-09-16 · 4 revisions tracked |
| Claim id | gb200-gb300-nvl72-rack-tdp-gb300-up-to-142-kw |