non-binding consumption connection inquiries at Fingrid, more than half related to data-center projects — against a €5.2B grid investment plan through 2035 intended to enable ~10 GW of new industrial demand
>100 GWobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| Scope | Inquiries, not a bankable queue: Fingrid's conditional connection-agreement model applies at ≥250 MW, connection lines normally take ~36 months after agreement, and southern-Finland consumption connections were temporarily tight through 2027. |
| As of | 2025-12 |
| Source | Fingrid FY2025 financial statements bulletin |
| Review | checking…review by 2026-10-22 · standard cadence |
| Recorded changes | none recorded |
| Claim id | fingrid-connection-inquiries-over-100-gw |