non-binding consumption connection inquiries at Fingrid, more than half related to data-center projects — against a €5.2B grid investment plan through 2035 intended to enable ~10 GW of new industrial demand

>100 GWobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeInquiries, not a bankable queue: Fingrid's conditional connection-agreement model applies at ≥250 MW, connection lines normally take ~36 months after agreement, and southern-Finland consumption connections were temporarily tight through 2027.
As of2025-12
SourceFingrid FY2025 financial statements bulletin
Reviewchecking…review by 2026-10-22 · standard cadence
Recorded changesnone recorded
Claim idfingrid-connection-inquiries-over-100-gw