distribution / pad-mount transformer lead time (sub-HV class) — distribution average ~30 wk (vs 100+ wk 2023 peak); pad-mount three-phase delays growing, dry-type 20–40 wk
~20–40 wkobserved
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| As of | 2025 |
| Source | Wood Mackenzie Q2 2025 supply-chain survey via EEPower; POWER Magazine (2026-01) |
| Review | checking…review by 2026-08-28 · fast cadence |
| Recorded changes | last 2026-07-12 |
| Claim id | distribution-pad-mount-transformer-lead-time |