data-center load dropped over a six-fault, 82 s sequence (NoVA, Jul 2024; NERC Level 3 alert 2026) — the swing go-live first exposes

~1.5 GWobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeLoad loss as seen by the grid. NERC's incident review found the affected data centers transferred their loads to backup power — static UPS, decentralized rack UPS, or DRUPS — in response to the disturbance. The figure is a loss of demand at the interconnection, not evidence that IT power was interrupted or that training jobs restarted.
CaveatThe approximately 1,500 MW is a local customer-side load reduction coincident with the six-fault sequence; NERC reports approximately 1,260 MW as the sustained drop at the third depression. The 2026 Level 3 alert is a separate regulatory action concerning this class of risk. A second, larger occurrence followed on 2026-07-22: ~3.8 GW dropped on a single normally-cleared Ashburn 230 kV fault (see companion key number) — two vintages of the same failure mode, so do not size to the 2024 event as the high-water mark.
As of2024-07
SourceNERC Incident Review (Jan. 8, 2025); NERC Level 3 Computational Load Alert (May 4, 2026) · Incident Review pp. 1–3: approximately 1,500 MW, six successive faults in an 82-second period, exclusively data-center-type load; Level 3 Alert pp. 1 and 7–8: May 4, 2026 alert and Essential Action #5
Reviewchecking…review by 2026-12-22 · standard cadence
Recorded changeslast 2026-08-24 · 4 revisions tracked
Claim iddata-center-load-dropped-over-a-six-fault-82-s