Delay-LD daily rates on large data-center construction projects, per Bracewell LLP (December 2025)

Thousands to tens of thousands of dollars per dayobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeUS law-firm practice commentary on data-center construction contracts: a qualitative range for the daily delay-LD rate, not a survey of executed contracts. The article says caps are often expressed as a percentage of contract value but gives no percentage.
CaveatPractice commentary, not contract data; private data-center LD rates and cap percentages are not published.
As of2025-12
SourceBracewell LLP, "Managing Contractual Risk in Data Center Construction: 10 Key Questions Answered" (December 3, 2025; republished in Surety Bond Quarterly, March 6, 2026) · Q2 'How Are Liquidated Damages Typically Calculated in Construction Contracts?': 'In large-scale projects like data centers, these rates can range from thousands to tens of thousands of dollars per day.' Q4 'How Can Data Center Construction Contracts Limit Exposure to Liquidated Damages?': caps on total liability 'often expressed as a percentage of the contract value'
Reviewchecking…review by 2027-04-19 · standard cadence
Recorded changeslast 2026-10-19
Claim iddata-center-delay-ld-daily-rate-range