FERC Order No. 907 effective date, approving CIP-015-1 (INSM); NERC lists CIP-015-1 effective Oct 1, 2028, with the other specified applicable systems Oct 1, 2030

Sep 2, 2025observed

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeSep 2, 2025 is the effective date of FERC Order No. 907, not a compliance date. NERC's effective-date bulletin lists CIP-015-1 as effective Oct 1, 2028 — the first calendar quarter after the 36-month implementation interval — with a further 24 months, to Oct 1, 2030, for the other specified applicable systems. The dates are not the order date plus three and five years.
As of2025
SourceFERC Order No. 907; Federal Register · FERC Order No. 907: Federal Register p. 28889 (DATES) and p. 28898 (Section VII), effective September 2, 2025; NERC standards & compliance bulletin (2025-11-24) p. 8 for the Oct 1, 2028 / Oct 1, 2030 effective dates
Reviewchecking…review by 2026-09-26 · standard cadence
Recorded changeslast 2026-06-29
Claim idcip-015-insm-effective-date-phased-compliance