The Definitive Guide toAI Data Centers
Ask the GuideAboutAccount
Guide › Numbers register › Claim

Celtic Interconnector Ireland-France capacity (575 km route, ~500 km subsea); expected commissioning Q4 2028 — slipped from the original 2027 schedule

700 MWobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
CaveatCommissioning date has slipped twice (2027 → spring 2028 → Q4 2028); treat the schedule as at-risk.
As of2026-07
SourceEirGrid
Reviewchecking…review by 2026-10-22 · standard cadence
Recorded changesnone recorded
Claim idceltic-interconnector-ireland-france-700-mw

Where the guide uses it

Not quoted in a chapter yet; it is kept in the curated register.

← Full numbers register — every date-stamped figure in the guide, with revision history.