busway / busduct lead time — standard runs average ~27 wk (VAWN 2026-06), custom engineered runs at the top of the range; fabrication can't start until final dimensioned drawings

~27–52 wkobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
As of2026
SourceCPM Pros; VAWN electrical lead-time index (2026-06)
Reviewchecking…review by 2026-08-29 · fast cadence
Recorded changeslast 2026-07-12
Claim idbusway-busduct-lead-time-standard-runs-average