total Sweden-Finland transfer capability in each direction after the 380 km Aurora Line was commissioned on 13 Nov 2025 (+~900 MW FI→SE / +~800 MW SE→FI) — which also raised permitted withdrawal around Luleå/Boden from 345 to 745 MW

~1,900 MWobserved

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
ScopeNext planned link, Fenno-Skan 3 (~800 MW), is not expected until ~2038.
As of2025-11
SourceFingrid; Svenska kraftnät
Reviewchecking…review by 2026-10-22 · standard cadence
Recorded changesnone recorded
Claim idaurora-line-finland-sweden-transfer-capability