aeroderivative turbine lead time (refurb under 12 mo; some cores quoted to ~243 weeks) — new-build order slots quoted for 2028–2030 as of 2026

18–36 mo+observed

Value kindobserved — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range.
As of2025
Source2025 synthesis; Data Center Frontier / power-eng aeroderivative coverage (2026) · Market overview; aeroderivative gas-turbine lead times are stated as 18–36 months.
Reviewchecking…review by 2026-09-16 · fast cadence
Recorded changeslast 2026-07-12 · 3 revisions tracked
Claim idaeroderivative-turbine-lead-time-refurb-under