aeroderivative turbine lead time (refurb under 12 mo; some cores quoted to ~243 weeks) — new-build order slots quoted for 2028–2030 as of 2026
18–36 mo+observed
| Value kind | observed — Reported measurements, counts, and specifications keep the precision and scope stated by their source; an exact specification is not treated as a range. |
|---|---|
| As of | 2025 |
| Source | 2025 synthesis; Data Center Frontier / power-eng aeroderivative coverage (2026) · Market overview; aeroderivative gas-turbine lead times are stated as 18–36 months. |
| Review | checking…review by 2026-09-16 · fast cadence |
| Recorded changes | last 2026-07-12 · 3 revisions tracked |
| Claim id | aeroderivative-turbine-lead-time-refurb-under |