AI data centers in Ireland & Dublin

Dublin was the canonical moratorium market; since December 2025 it is the canonical conditional market. CRU's connection policy reopened applications — priced in matched dispatchable generation and an 80%-additional-renewables obligation — while EirGrid still classifies Greater Dublin itself as fully constrained. It remains the leading indicator for how European grid operators gate data-center load.

Where the deltas are derived

Ireland & Dublin in the register

FigureValueAs ofSource
EirGrid classification of Greater Dublin for new data-centre connections — new large connections cannot be accommodated before major network reinforcement (short-circuit limits); surrounding areas also expected to remain constrainedfully constrainedMay 2026EirGrid
contracted data-centre grid demand in Ireland, mostly in Greater Dublin — nearly one-third of national electricity demand if all sites connect and use their full contracts~2 GWMay 2026EirGrid
indicative near-term data-centre connection headroom outside Dublin, concentrated at selected Galway, Limerick and Cork 220 kV nodes — subject to individual assessment, with delivery potentially mid-2030s~150-300 MWMay 2026EirGrid
projected installed data-centre IT capacity in Ireland by 2030 under existing grid contracts (+19% vs the 2025 base of ~1,543 MW); a further ~1.4 GW development pipeline is not grid-approved~1,843 MWJun 2026Department of Enterprise / KPMG (Jun 2026)
Celtic Interconnector Ireland-France capacity (575 km route, ~500 km subsea); expected commissioning Q4 2028 — slipped from the original 2027 schedule700 MWJul 2026EirGrid
share of all Uisce Éireann drinking water supplied to data centres — small nationally, but Greater Dublin demand already brushes maximum sustainable source capacity (up to ~680 ML/day on warm days) pending the Shannon-source Water Supply Project<0.3%Jul 2026Uisce Éireann
Irish corporation tax on trading income — with the 15% Pillar Two minimum effective rate applying to in-scope groups (≥€750M global turnover in 2 of the preceding 4 years), i.e. every hyperscaler; FDI posture remains supportive but plan-led and renewables-conditioned12.5% headline / 15% Pillar TwoJul 2026Revenue; Department of Finance
Large Energy User Action Plan (Jan 2026) enabling actions — including legislating the Private Wires Policy during 2026 and a National Planning Statement for green-energy parks co-locating large loads with renewables17 actionsJan 2026Department of Enterprise LEAP
CRU/2025236 (Dec 2025) conditions to connect new large energy users: sites ≥10 MVA must bring matching dispatchable generation/storage (separately connected, market-participating) and meet ≥80% of annual demand from additional Irish renewable generation on a six-year glide path≥80% additional renewables + matched dispatchableDec 2025CRU decision paper CRU/2025236
installed operational data-centre IT capacity in Ireland (72 buildings, 36 sites, 25 operators) — ~99% of it in the Greater Dublin Area, ~1.36 GW of it hyperscale~1,543 MWDec 2025Department of Enterprise / KPMG (Jun 2026)
share of Ireland's total metered electricity consumed by data centres in 2025 (7,663 GWh of 32,986 GWh, +10% YoY; up from ~5% in 2015, 21% in 2023, 22% in 2024) · Ch 3.1323%2025 (published Jul 2026)CSO
carbon intensity of Irish electricity consumption, 2025 provisional (generation + own-use + network losses; gas ~40% of supply)~198 gCO2/kWh2025 (provisional)SEAI conversion factors
renewable share of Irish electricity supply in 2025 (wind 32.0%; gas 40.0%, net imports 16.3%)40.9%2025 (interim)SEAI Interim 2025 National Energy Balance (May 2026)
SEM (all-island Irish market) day-ahead average power price for calendar 2025 — ~34% above the ~€85/MWh 2025 European Power Benchmark (EU range €41-116/MWh)~€114/MWh2025SEMOpx; European Commission DG Energy
EU EED Art. 12 reporting threshold (installed IT power); ~31 data points incl. PUE/WUE/ERF/REF · Ch 3.9≥500 kW2024 (in force)European Commission; Delegated Reg. (EU) 2024/1364

Regulatory watchlist

RuleThresholdStatusVerified
EUEED Art. 26 (Dir. 2023/1791) — waste-heat recovery cost-benefit analysis required>1 MW total rated inputIn force2026-06
EUEED Art. 12 / Delegated Reg. (EU) 2024/1364 — mandatory DC energy/water/PUE reporting to EU database≥500 kW installed ITIn force (annual reporting)2026-06
EUCSRD 'Omnibus' simplification — sustainability-reporting scope & timelines being amendedlarge-undertaking thresholds under revisionPENDING — verify final scope/dates2026-06

What this means for your schedule

New applications have been possible since May 2026 (EirGrid's DCCOPP v3), but the terms are the schedule: a connection now means three linked applications — the demand site, nominated dispatchable generation, and nominated additional renewables — and Greater Dublin remains fully constrained regardless. The live paths are regional Ireland (EirGrid points to ~150–300 MW of indicative headroom at Galway, Limerick and Cork nodes, some of it mid-2030s delivery) with the generation stack built into the application, or treating Ireland as a latency/sovereignty satellite to capacity built elsewhere in Europe.

Turn this into dates: the lead-time planner reverse-schedules every long-lead PO from your target — the queue figures above set which packages are already late.