HV · High voltage

The transmission-class voltage at the point of interconnection and the GSU transformer; HV breakers and switchgear are among the longest-lead items on a campus schedule.

Current numbers

~128–160+ wkHV/substation power transformer lead time (standard); up to ~60 months in constrained markets — often the schedule's long poleas of 2026 · register ↗
~128–160+ wkHV/substation transformer lead time (≈144 wk GSU; up to ~60 mo constrained) — OFE-by-default, pre-GCas of 2026 · register ↗
~128–160+ wkHV / GSU power-transformer lead time setting equipment-delivery risk in supply agreements; up to ~60 mo constrainedas of 2026 · register ↗