The Definitive Guide toAI Data Centers
Ask the GuideAboutAccount
Calculators › Cluster sizing — model → MW

Cluster sizing — model → MW

Size an inference fleet end to end: model parameters, quantization, KV cache and context length → VRAM per replica → active GPUs → installed racks, stranded capacity, facility megawatts, and fractional rental cost at a contract underwriting rate (GB300 NVL72 ~$5.00/GPU-hr, the SemiAnalysis InferenceX 'retail' rate (its glossary defines retail as a three-year reservation price); the $18.00 on-demand list is context only).

ScenarioNVIDIA GB300 NVL72 · 56 active / 72 installed GPUs · 1 racks · 0.14 MW IT · $9M programguide defaults (as of 2026-09)Edit the shared scenario →

Cluster sizing — model to megawatts

56 active / 72 installed GPUs · 0.16 MW at nominal TDP × PUE
VRAM per replica (weights 70 + KV 676 GB, +15% overhead)858 GB
Qualified GPUs per replica → replicas for demand (VRAM floor 3)8 × 7
Installed GPUs / stranded slots72 / 16
Installed racks (72/rack)1
Facility draw on installed units at nominal rack TDP × PUE (not the OEM facility-design provision or transient peak)0.16 MW
Rental cost on active GPUs at the underwriting rate$204,400/mo

The MW figure is an energy/TCO basis at nominal TDP. Electrical design uses the named rack's facility-design provision and transient peak (GB300 NVL72: 135 kW nominal, up to 142 kW facility basis, 155 kW peak) — three different numbers, never interchangeable → Ch 7.2. VRAM establishes only a memory floor. Enter a replica degree qualified for the named model, runtime, hardware, context and batch profile; supported degrees need not be powers of two. Purchase quantum is a separate SKU or contract input and is not inferred from rack density. Facility design power follows installed units, while rental cost follows the active fractional fleet. At long context the KV cache can dominate VRAM → Ch 9.7.

Worked decision — stated assumptions

All ledger inputs are assumed teaching values chosen to exercise this chapter’s method; they are not market quotes, OEM performance claims or operating records. Arithmetic uses the full entered precision.

Assumed inputs
InputValue
Model size70 B params
Bytes / param1 bytes
KV cache / token330 KB
Context length32000 tok
Concurrent requests / replica64 requests
Activation + framework overhead15 %
HBM per GPU288 GB
Peak demand50000 tok/s
Throughput / replica11200 tok/s
Serving capacity70 %
Qualified GPUs / replica8 GPUs
GPUs / rack72 GPUs
Purchase quantum72 GPUs
GPU TDP1400 W
Host overhead1.3393 × GPU TDP
PUE1.15 ratio
Underwriting rental rate18 $/GPU-hr

Illustrative purchase decision: assume a 70-billion-parameter model at one byte per parameter, 330 KB of KV cache per token, 32,000-token context, 64 concurrent requests and 15% framework overhead. Memory is (70 + 330 × 32,000 × 64 / 1,000,000) × 1.15 = about 858 GB per replica. Assume 288 GB per GPU and a separately qualified eight-GPU replica: the three-GPU memory floor does not replace that qualification.

Assume 50,000 output tokens/s peak demand, 11,200 tokens/s per qualified replica and 70% serving capacity. Round 50,000 / (11,200 × 0.70) up to seven replicas: 56 active GPUs. A stated 72-GPU purchase unit gives 72 installed GPUs, 16 stranded slots and one 72-GPU rack. At an assumed 135 kW nominal rack input and PUE 1.15, the nominal facility screen is about 155 kW. Fractional rental at an assumed $18/GPU-hour costs $1,008/hour for the active fleet.

Assume a $1,100/hour active-fleet rental allowance. The seven-replica case fits. Above 7 × 11,200 × 0.70 = 54,880 output tokens/s, demand needs an eighth replica: at 60,000 tokens/s, 64 active GPUs cost $1,152/hour and exceed the allowance, while the same 72-GPU purchase unit still fits. Acquire the exact serving qualification before committing the purchase.

Guide derivation. Method and handoff: Chapter 1.7 — The Requirements-and-Consequences Matrix.

These are transparent screening estimates, not final designs, financial advice, or project approvals. Replace every default with current project data and have the responsible project authorities validate the result. You can save, share a permalink, or export to CSV; see the full calculator suite.