The Definitive Guide toAI Data Centers
Ask the GuideAboutAccount
Regional guides › Texas & ERCOT

AI data centers in Texas & ERCOT

ERCOT's energy-only market and co-location with West Texas wind, solar, and gas can create project-specific power paths — priced in exposure to scarcity pricing, curtailment economics, and grid-islanding risk that the design basis must own.

Where the deltas are derived

Texas & ERCOT in the register

FigureValueAs ofSource
ERCOT issued Batch Zero Conditional Classification to service providers, subject to verification and cure conditions · Ch 3.2September 3, 2026: conditional classification issued2026-09-03ERCOT — Notice M-A080326-04, September 3, 2026; event confirmed by the official notice archive. Direct notice retrieval returned 403 on September 8.
on-site gas LCOE must be modeled for the named plant from heat rate, gas price, capacity factor, capex and financing, O&M, emissions and permits, interconnection and standby costsProject-specific LCOE2026-08-24U.S. Energy Information Administration
large-load interconnection requests ERCOT is tracking (~90% data centers; arc: 63 → 233 → 438 → 474 GW; more than 5x ERCOT's record peak demand). Batch Zero paused 2026-08-03 by gubernatorial directive; conditional classification issued 2026-09-03 · Ch 3.1~474 GW2026-08Abbott directive letter (2026-08-03, ~474 GW / ~90% DC); prior print 438+ GW (ERCOT, 2026-06-18). BNEF estimates the pause could delay ~50 GW. Operating sites unaffected.
Texas sales-tax revenue forgone to the data-center exemption (~$1B+/yr) · Ch 3.10~$3.3B / biennium2026-07Texas Comptroller via Senate Finance hearing (2026-07-27); Texas Tribune; Holland & Knight
Texas average commercial retail electricity price — among the lowest in the US (statewide all-in average; competitive-supply quotes in deregulated ERCOT territories run lower) · Ch 3.3~8.4¢/kWh2026-04EIA Electric Power Monthly, Table 5.6.A
ERCOT 'large load' threshold forcing full interconnection + protection study (25 MW = modeling) · Ch 4.275 MW2026ERCOT Large Load Integration; SB6
projected ERCOT data-center load in 2028; the same forecast reaches approximately 40.1 GW in 2030 · Ch 3.1~28.2 GW2025-12-15Electric Reliability Council of Texas
curtailment-enabled headroom at 0.5% in PJM / MISO / ERCOT (SPP also ~10 GW; Southern ~8 GW) · Ch 15.818 / 15 / 10 GW2025-02-11Duke Nicholas Institute, Rethinking Load Growth, February 2025
planned Stargate capacity across the Abilene flagship + five new US sites — multi-campus by necessity, not choice · Ch 8.8~7 GW2025OpenAI / Data Center Frontier
Texas average data-center water intensity; ~49 bn gal statewide by end-2025 · Ch 3.7~793 gal/MWh2025Houston Advanced Research Center (HARC), 'Thirsty Data and the Lone Star State'
Texas Chapter 312 property-tax abatement of eligible incremental property value, locally negotiated for up to 10 years · Ch 3.10up to 100%2025Texas Comptroller of Public Accounts

Regulatory watchlist

RuleThresholdStatus / next actionSourceVerifiedReview by
US (Texas) — ERCOT Planning Guide §9 / PGRR145 — Batch Zero large-load integrationNew load ≥75 MW; existing-load increase ≥75 MW; specified point-of-interconnection changesBatch Zero implemented; PUCT SB 6 rulemaking remains a separate live process
Next: Track Batch Zero studies and PUCT Project 58481
Electric Reliability Council of Texas2026-08-242026-09-30

What this means for your schedule

After the governor ordered a project-by-project audit of data centers, ERCOT paused Batch Zero classification and studies and said it will not let new data-center loads energize until verification is complete. The conditional classification issued since is not a study result, a service offer or permission to energize, and ERCOT says the Batch Zero study will miss its original target date. Until the audit and the study clear, obtain for each ERCOT project the applicable large-load study path, host-utility agreement, upgrade scope, curtailment obligations, power rights, and dated milestones; neither a market label nor co-location guarantees an earlier service date. The design basis must also own scarcity-hour economics, an SB6-class curtailment response (ride-through, on-site generation, or workload shedding), and West Texas water reality. Budget the hedge strategy with the same seriousness as the substation.

Turn this into dates: the lead-time planner reverse-schedules every long-lead PO from your target. Use your host utility's dated service milestones and your own need-by dates to see which packages are late; regional queue totals do not set your connection date.