The Definitive Guide toAI Data Centers
Ask the GuideAboutAccount
Regional guides › Northern Virginia & PJM

AI data centers in Northern Virginia & PJM

The densest data-center market on earth sits inside PJM, where interconnection queues, transmission buildout, and county-level land-use politics now set the pace — not capital. Data-center alley's grid position makes speed-to-power the defining regional constraint.

Where the deltas are derived

Northern Virginia & PJM in the register

FigureValueAs ofSource
Northern Virginia data center inventory tracked by CBRE at the end of 2025, with about 96% of 2026 scheduled supply already committed and vacancy at 0.5% · Ch 3.13~4,040 MWend-2025 (CBRE release 18 March 2026)CBRE, North America Data Center Trends H2 2025 (press release, 18 March 2026)
Share of generation/storage capacity requesting interconnection in 2000-2020 that reached commercial operation by end-2025; 75% withdrew (LBNL, Queued Up: 2026 Edition) · Ch 3.213%end-2025LBNL, Queued Up: 2026 Edition
data-center share of PJM's $16.4B capacity-auction cost — the cost-shift driver · Ch 3.11~$6.3B (38%)2026-07-20Monitoring Analytics (Joseph Bowring), reported by Utility Dive, July 20, 2026
Virginia data-center sales-and-use tax exemption benefit reported for FY2025; the final 2026 budget retained the exemption and added a separate data-center electricity consumption tax · Ch 3.10~$1.94B (FY2025)2026-07Virginia Department of Taxation, DCRSUT Exemption Report (RD40, 2026)
Virginia data-center electricity consumption tax, gross rate, July 1, 2026 through June 30, 2028 · Ch 3.3$0.011/kWh2026-06-29Virginia HB30, 2026 Special Session I, Chapter 1, adopted June 29, 2026, Item 3-5.24
PJM generation EIT study and readiness deposits under the tariff accepted June 9, 2026 · Ch 2.1$500k study + $15k/MW2026-06-09FERC June 9, 2026 order, ER26-1563-000; accepted Part X effective July 31, 2026.
PJM transmission services for co-located load (interim non-firm, Firm Contract Demand, Non-Firm Contract Demand), ordered by FERC 18 Dec 2025; rates and terms set on rehearing/compliance 18 Jun 2026, further tariff compliance due ~Aug 2026 · Ch 3.43 new2026-06FERC, PJM Interconnection, 193 FERC ¶ 61,217 (18 Dec 2025) and 195 FERC ¶ 61,209 (18 Jun 2026), Docket EL25-49
FERC PJM co-location order: 3 new transmission services; BTM transition to Dec 18, 2028 · Ch 15.8Dec 18, 20252025-12-18Federal Energy Regulatory Commission, December 18, 2025 fact sheet on PJM co-location; primary-source account of the three-service direction.
added to a typical Dominion residential bill in 2026 by the approved base-rate change · Ch 3.11$11.24/mo2025-11-25Virginia SCC, 2025 Dominion biennial review, November 25, 2025
curtailment-enabled headroom at 0.5% in PJM / MISO / ERCOT (SPP also ~10 GW; Southern ~8 GW) · Ch 15.818 / 15 / 10 GW2025-02-11Duke Nicholas Institute, Rethinking Load Growth, February 2025
PJM generator interconnection: application-to-commercial-operation timeline (vs <2 yr in 2008); a generation statistic, not a large-load service timeline · Ch 3.1>8 yr2025RMI / PJM filings
data-center load withdrawn from the grid as sites transferred to backup during the six-fault, 82-second Northern Virginia disturbance on July 10, 2024 · Ch 2.2~1.5 GW in 82 s2024-07NERC incident review / Level 3 Alert (2026); Utility Dive
potable water used by Loudoun County (VA) data centers in 2023 (~250% increase) · Ch 15.4~899M gal2023Loudoun Water; Nixon Peabody

What this means for your schedule

For a near-term energization, require the host utility to name the applicable load-study path, service agreement, upgrade scope, power rights, and dated milestones; generator-queue statistics do not establish that schedule. Treat county land-use approval as a separate critical path, and watch the FERC co-location dockets because generator-adjacent service still depends on the approved project structure.

Turn this into dates: the lead-time planner reverse-schedules every long-lead PO from your target. Use your host utility's dated service milestones and your own need-by dates to see which packages are late; regional queue totals do not set your connection date.